To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Accepting completion of improvements for the Subdivision Agreement for subdivision SD06-09131 (cross-reference development plan DP04-03015), Bay Point area.
Recommendation: Recommendation of the County Administrator

RECOMMENDATIONS:
ADOPT Resolution accepting completion of improvements for the Subdivision Agreement for subdivision SD06-09131 (cross-reference development plan DP04-03015) for a project developed by Jasraj Singh and Tomas Baluyut, as recommended by the Public Works Director, Bay Point area. (District V)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
The developer has completed the improvements per the Subdivision Agreement, and in accordance with Title 9 of the County Ordinance Code.
CONSEQUENCE OF NEGATIVE ACTION:
The completion of improvements will not be accepted and the warranty period will not begin.
c: J. LaRocque-Engineering Services, A. Vazquez-Engineering Services, J. Ma- Engineering Services, J. Hernandez-Engineering Services, T. Shepherd-Design/Construction, M. Cordis- Maintenance, A. Ruyters-Surveys, C. Halford-Mapping, W. Gardizi-Finance, Ruben Hernandez- DCD, Jasraj Singh, Developers Insurance and Indemnity, Viking Bond Service, T. August 20, 2027
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
body
IN THE MATTER OF: Accepting completion of improvements for the Subdivision Agreement for subdivision SD06-09131 (cross-reference development plan DP04-03015) for a project developed by Jasraj Singh and Tomas Baluyut, as recommended by the Public Works Director, Bay Point area. (District V)
WHEREAS, the Public Works Director has notified this Board that the improvements in subdivision SD06-9131 have been completed as provided in the Subdivision Agreement with Jasraj Singh and Tomas Baluyut, heretofore approved by this Board in conjunction with the filing of the Subdivision Map.
WHEREAS, these improvements are located at the intersection of Mountain View Avenue and Willow Pass Road.
NOW, THEREFORE, BE IT RESOLVED that the improvements have been COMPLETED as of October 20, 2026, thereby establishing the six-month terminal period for the filing of liens in case of action under said Subdivision Agreement:
DATE OF AGREEMENT: May 15, 2007
NAME OF SURETY: Developer’s Surety and Indemnity
BE IT FURTHER RESOLVED the payment (labor and materials) surety for $30,450.00, Bond No. 761783S issued by the above surety be RETAINED for the six-month lien guarantee period until April 20, 2027, at which time the Board AUTHORIZES the release of said surety less the amount of any claims on file.
BE IT FURTHER RESOLVED that Mountain View Avenue for the hereinafter described public improvements, have been constructed in accordance with the Subdivision Agreement and are ACCEPTED AS COMPLETE.
BE IT FURTHER RESOLVED that improvements within Parcel A for the hereinafter described private road, as shown and dedicated for Homeowners of Subdivision 9131 use on the Final Map of Subdivision SD06-09131 filed May 18, 2007, in Book 504 of final maps at Page 3, Official Records of Contra Costa County, State of California, have been COMPLETED and are NOT ACCEPTED, at this time.
BE IT FURTHER RESOLVED that the beginning of the warranty period is hereby established, and the $1,000.00 cash deposit (Auditor's Deposit Permit No. 479717, dated March 13, 2007) made by Jasraj Singh, and the performance-maintenance surety bond rider for $9,135.00, Bond No. 761783S issued by Developers Surety and Indemnity Company RETAINED pursuant to the requirements of Section 94-4.406 of the Ordinance Code until release by this Board.