Title: Livorna Park Revitalization Project Review
Attachments: 1. Livorna Park 65% OPC (Const Contract Est), 2. Livorna_Park_AMAC_Budget_Analysis.docx
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.

Advisory Board: Alamo Municipal Advisory Council

Subject:  Livorna Park Improvements Project

 

Information:

 

The Livorna Park Improvements project is currently at the 65% design stage, with a total estimated cost of $4.09 million. While the overall layout and major systems are defined, costs are being refined as the project approaches final bidding decisions.

 

Please note: The Municipal Advisory Council (MAC) is reviewing the project to consider the elimination of specific high-cost items to manage the budget. It is critical to understand that any redesign of the current plans will result in additional costs and may impact the target opening date of July 2027.

 

Where the Project Stands

The Livorna Park Improvements project is currently at the 65% design stage, meaning:

                     Overall layout, features, and major systems are defined

                     Costs are refined but not final

                     The project is approaching 95% design and bidding decisions

 

Key Upcoming Milestones

                     April 7, 2026: MAC review

                     May-June 2026: Final design (95-100%) and Board of Supervisors approvals

                     Summer 2026: Bid and award

                     Fall 2026: Construction start

                     July 2027: Target park opening

 

Schedule Risks

                     Overlap between final design and Board approval could delay bidding

                     Construction runs through winter with no clear weather contingency

 

Total Project Budget

Current Total Estimated Cost: $4.09 Million

Category

Cost

%

Construction

$3.30M

80%

Construction Management

$340K

8%

Design (Consultant + County)

$442K

11%

Environmental (CEQA)

$15K

<1%

 

Construction Cost Breakdown (Key Drivers)

Playground (Largest Cost Driver)

                     $1.10M (38% of construction)

                     Includes:

o                     Equipment: $442K

o                     Safety surfacing: $246K

o                     Shade sails: $165K

o                     Freight + install: ~$200K

 

Splash Pad / Water Features

                     $462K (16%)

 

Breakdown:

                     Equipment: $35K

                     Installation: $221K

                     Mechanical systems: $113K

 

Walls & Structures

                     $245K (8.6%)

                     Entry arbor alone: $115K

 

Site Furnishings

                     $227K (8%)

                     Includes:

o                     Benches ($60K)

o                     Tables, trash cans, shade structures

o                     $20K shipping line item

 

Hardscape (Paving, Courts)

                     ~$290K combined

                     Includes:

o                     Concrete walkways

o                     Basketball court

o                     Bocce improvements

 

Landscaping & Irrigation

                     $147K (5%)

 

Utilities, Grading & Drainage

                     $134K (4.7%)