To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Accepting completion of landscape improvements without the need of a warranty period for subdivision SD14-09341, San Ramon (Doughty Valley) area.
☒Recommendation of the County Administrator ☐ Recommendation of Board Committee

RECOMMENDATIONS:
ADOPT Resolution accepting completion of landscape improvements without the need of a warranty period, for subdivision SD14-09341, for a project developed by Shapell Homes, a Division of Shapell Industries, Inc., a Delaware Corporation, as recommended by the Public Works Director, San Ramon (Dougherty Valley) area. (District II)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
The developer has completed the landscape improvements without the need for an agreement and in accordance with Title 9. The landscape improvements have met the guaranteed performance standards for longer than would be required for a standard warranty period. The landscape improvements were not accepted when initially completed due to a mapping concern that has since been resolved.
CONSEQUENCE OF NEGATIVE ACTION:
The completion of landscape improvements will not be accepted.
c: Jocelyn LaRocque -Engineering Services, Kellen O’Connor - Engineering Services, Devon Patel-Engineering Services, Theresa Shepherd-Design/Construction, Chris Lau-Maintenance, Chris Hallford-Mapping, Ciara Herrold-Finance, C. Low-City of San Ramon, Shapell Homes
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
body
IN THE MATTER OF: Accepting completion of landscape improvements without the need of a warranty period, for subdivision SD14-09341, for a project developed by Shapell Homes, a Division of Shapell Industries, Inc., a Delaware Corporation, as recommended by the Public Works Director, San Ramon (Dougherty Valley) area. (District II)
WHEREAS, these improvements are approximately located near Dougherty Road and Trefoil Road, and Dougherty Road and Hibiscus Road.
The Public Works Director has notified this Board that the landscaping improvements for SD14-09341, have been completed, heretofore approved by this Board.
NOW, THEREFORE, BE IT RESOLVED that the landscape improvements have been COMPLETED as of June 24, 2025, thereby establishing the six-month terminal period for the filing of liens in case of action.
BE IT FURTHER RESOLVED that the San Ramon City Council shall accept the landscape improvements for maintenance and ownership in accordance with the Dougherty Valley Memorandum of Understanding.
c: Jocelyn LaRocque -Engineering Services, Kellen O’Connor - Engineering Services, Devon Patel-Engineering Services, Theresa Shepherd-Design/Construction, Chris Lau-Maintenance, Chris Hallford-Mapping, Ciara Herrold-Finance, C. Low-City of San Ramon, Shapell Homes
end