File #: RES 2025-268    Version: 1 Name:
Type: Consent Resolution Status: Passed
File created: 7/2/2025 In control: BOARD OF SUPERVISORS
On agenda: 8/5/2025 Final action: 8/5/2025
Title: ADOPT Resolution No. 2025-268 approving and authorizing the Public Works Director, or designee, to fully close a portion of Bayo Vista Street, on August 14, 2025, from 7:30 a.m. through 5:30 p.m., for the purpose of a utility pole replacement, San Pablo area. (No fiscal impact)

To:                                           Board of Supervisors

From:                                          Warren Lai, Public Works Director/Chief Engineer

Report Title:                     Approve and Authorize to fully close a portion of Bayo Vista Street on August 14, 2025, from 7:30 a.m. through 5:30 p.m., for the purpose of a utility pole replacement, San Pablo area.

Recommendation of the County Administrator Recommendation of Board Committee

 

RECOMMENDATIONS:

ADOPT Resolution approving and authorizing the Public Works Director, or designee, to fully close a portion of Bayo Vista Street, near 1638 Bayo Vista Street, on August 14, 2025, from 7:30 a.m. through 5:30 p.m., for the purpose of replacing a utility pole, San Pablo area. (District I)

 

FISCAL IMPACT:

No fiscal impact.

 

BACKGROUND:

Due to the narrow road width of Bayo Vista Street at the work site, Pacific Gas & Electric Company (PG&E) has requested the road closure to replace the existing utility pole. There is insufficient road width to set up and operate boom trucks and safely maintain through traffic. Applicant shall follow guidelines set forth by the Public Works Department.

 

CONSEQUENCE OF NEGATIVE ACTION:

Applicant will be unable to close the road to complete planned utility pole replacement.

 

c: Kellen O’Connor-Engineering Services, Marke Smith-Engineering Services, Devon Patel-Engineering Services, Bob Hendry-Engineering Services, Chris Lau-Maintenance, Sheriff’s Office, CHP

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board

 

body

IN THE MATTER OF: Approving and Authorizing the Public Works Director, or designee, to fully close a portion of Bayo Vista Street, near 1638 Bayo Vista Street, on August 14, from 7:30 a.m. through 5:30 p.m., for the purpose of replacing a utility pole, San Pablo area. (District I)

 

                                                                    

     RC25-22

                     

 

NOW, THEREFORE, BE IT RESOLVED that permission is granted to Pacific Gas & Electric Company to fully close a portion of Bayo Vista Street, near 1638 Bayo Vista Street, except for emergency traffic, local residents, US Postal Service and garbage trucks, on August 14, 2025, from 7:30 a.m. through 5:30 p.m., subject to the following conditions:

 

1. Traffic will be detoured via roads identified in a traffic control plan, reviewed by the Public Works Department. Emergency vehicles, residents within the construction area and essential services will be allowed access as required.

 

2.  All signings be in accordance with the California Manual on Uniform Traffic Control Devices.

 

3.                     Pacific Gas & Electric Company shall comply with the requirements of the Ordinance Code of Contra Costa County.

 

4.                     Provide the County with a Certificate of Insurance in the amount of $1,000,000.00 for Comprehensive General Public Liability which names the County as an additional insured prior to permit issuance.

 

5.                     Obtain approval for the closure from the Contra Costa County Sheriff’s Office and the Contra Costa Fire Protection District.

 

end