Legislation Details

File #: RES 2026-159    Version: 1 Name:
Type: Consent Resolution Status: Agenda Ready
File created: 4/9/2026 In control: BOARD OF SUPERVISORS
On agenda: 4/28/2026 Final action:
Title: ADOPT Resolution No. 2026-159 accepting as complete, the contracted work performed by Sletten Construction Inc., for the West County Re-entry, Treatment and Housing (WRTH) Project, as recommended by the County Administrator, Richmond area. (No fiscal impact)
Attachments: 1. Recordable Resolution, 2. 2260413 WRTH Request for Release of Retention Response_final, 3. WRTH Request for Substantial Completion response 4-7-26
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.

To:                                           Board of Supervisors

From:                                          Monica Nino, County Administrator

Report Title:                     Adopting a Resolution accepting as complete the contracted work performed by Sletten Construction, Inc., for the West County Re-entry, Treatment and Housing (WRTH) Project, as recommended by the County Administrator, Richmond area. (No fiscal impact)

Recommendation of the County Administrator Recommendation of Board Committee

 

RECOMMENDATIONS:

ADOPT Resolution accepting as complete the contracted work performed by Sletten Construction, a Montana Corporation, for the West County Re-Entry, Treatment and Housing Project, located at 5555 Giant Highway, Richmond, CA.

 

AUTHORIZE the Auditor-Controller to release the retention associated with the WRTH Project.

 

FISCAL IMPACT:

There is no fiscal impact associated with accepting completion of contracted work, the retention funds have been withheld from payments in accordance with the contract documents.

 

BACKGROUND:

Contra Costa County Contracted with Sletten Construction Company for the construction of the West County Re-Entry, Treatment and Housing (WRTH), at the West County Detention Facility in Richmond.

Contract Summary:

                     Initial Contract Amount:                                           $  95,500,000

                     Owner Contingency Allowance:                     $    2,846,249                     

                     Total Change Orders:                                                                $    8,468,826

                     Final Contract Total:                                                                $106,815,075 (inclusive of mutually agreed adjustments)

 

The WRTH project was substantially completion on March 26, 2026. All required permit inspections have been completed and officially approved. The County Administrator’s Office has performed a final review of the site and verified that the work meets all contractual specifications.

 

Consequently, the County Administrator’s office recommends that the Board adopt the resolution formally accepting the contract work as complete to initiate the final closeout process.

 

CONSEQUENCE OF NEGATIVE ACTION:

Accepting the contract as complete is standard procedure and allows for proper closeout of the contract. Failure to accept the work as complete will:

1.                     Extend the statutory period for filing stop payment notices and bond claims.

2.                     Cause the County to incur unnecessary additional expenses for extended contract administration and delayed retention release.