To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Approving the eleventh extension of the Subdivision Agreement for subdivision SD91-07553, Alamo area.
☒Recommendation of the County Administrator ☐ Recommendation of Board Committee

RECOMMENDATIONS:
ADOPT Resolution approving the eleventh extension of the Subdivision Agreement for subdivision SD91-07553, for a project being developed by Alamo Land Investors, LLC and Alamo 37, LLC, as recommended by the Public Works Director, Alamo area. (District II)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
The termination date of the Subdivision Agreement needs to be extended. The developer has not completed the required improvements and has requested more time. (Approximately 0% of the work has been completed to date.) By granting an extension, the County will give the developer more time to complete improvements and keeps the bond current.
CONSEQUENCE OF NEGATIVE ACTION:
The termination date of the Subdivision Agreement will not be extended, and the developer will be in default of the agreement, requiring the County to take legal action against the developer and surety to get the improvements installed, or revert the development to acreage.
c: J. LaRocque-Engineering Services, M. Smith-Engineering Services, T. Shepherd-Design/Construction, P. Tehaney- Design/Construction, R. Hernandez-DCD, Alamo Land Investors, LLC and Alamo 37, Lexon Insurance Company, T-10/12/2026
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
body
IN THE MATTER OF: Approving the eleventh extension of the Subdivision Agreement for subdivision SD91-07553, for a project being developed by Alamo Land Investors, LLC and Alamo 37, LLC, as recommended by the Public Works Director, Alamo area. (District II)
WHEREAS, the Public Works Director having recommended that he be authorized to execute the eleventh agreement extension which extends the subdivision agreement between Alamo Land Investors, LLC and Alamo 37, LLC and the County for construction of certain improvements in SD91-07553, Alamo area, through January 12, 2027.
APPROXIMATE PERCENTAGE OF WORK COMPLETE: 0%
ANTICIPATED DATE OF COMPLETION: 2030
BOND NO.: LICX1203868 Date: October 2, 2024
REASON FOR EXTENSION: The improvement plans are currently being updated to comply with the most recent applicable codes. Groundbreaking anticipated in 2027 (grading), improvements in 2028 (under grounding), construction in 2029 (vertical building).
NOW, THEREFORE, BE IT RESOLVED that the recommendation of the Public Works Director is APPROVED.
end