Skip to main content
Contra Costa County Header
File #: 25-3000    Version: 1 Name:
Type: Consent Item Status: Passed
File created: 7/2/2025 In control: BOARD OF SUPERVISORS
On agenda: 7/22/2025 Final action: 7/22/2025
Title: REJECT all bids received on June 5, 2025 for the Antioch Library Electrical Systems Upgrades Project and AUTHORIZE the Public Works Director, or designee, to re-advertise the bid, Antioch Area. (68% Measure X Funds, 21% California State Library Grant – Building Forward Grant, 11% Measure X and Library Funds)

To:                                          Board of Supervisors

From:                                          Warren Lai, Public Works Director/Chief Engineer

Report Title:                     REJECT bids and RE-ADVERTISE and solicit new bids for the Antioch Library Electrical Systems Upgrades Project, 501 W. 18th Street, Antioch

Recommendation of the County Administrator Recommendation of Board Committee

 

RECOMMENDATIONS:

(1)                     REJECT all bids received on June 5, 2025, for the Antioch Library Electrical Systems Upgrade Project, and

 

(2)                     ORDER any bid bonds posted by the bidders to be exonerated and any checks or cash submitted for security to be returned, and

 

(3)                     AUTHORIZE the Public Works Director, or designee, to re-advertise and solicit new bids for the Antioch Library Electrical Systems Upgrade Project.

 

FISCAL IMPACT:

Estimated construction cost $1,439,403. $978,320 (68%) will be funded through Measure X funds, $307,454 (21%) will be funded through California State Library Building Forward Grant (SB 129), and $153,726 (11%) will be funded through Measure X and Library Funds. 

 

BACKGROUND:

The above advertisement was previously approved by the Board of Supervisors, plans and specifications were filed with the Board, and bids were invited by the Public Works Director. On June 5, 2025, the Public Works Department received bids from the following contractors:

 

BIDDER

BID AMOUNT

CB2 Builders Inc

$802,300

One Workplace Construction LLC d/b/a Vantis, Inc.

$1,113,600

 

In reviewing the bids, Public Works determined that neither bid was responsive.

Therefore, the Public Works Department Director recommends to the Board of Supervisors to exercise its discretion to reject all bids pursuant to the Notice to Bidders and authorize the Public Works Director to re-advertise the above project.

 

CONSEQUENCE OF NEGATIVE ACTION:

 

If re-advertising of the project is not authorized, the project will not be constructed, the electrical system will remain out of date and insufficient for modern power requirements in libraries, the lighting will not be energy efficient and aligned with the County's Climate Action Plan, and the parking lot will not meet accessibility standards.  Furthermore, the Library Department risks losing grant funding for the proposed project if not completed within the timelines outlined by the grant.