Title: APPROVE and AUTHORIZE the Public Works Director, or designee, to advertise for Livorna Park Renovation Project at 2615 Miranda Avenue, Alamo area. (100% County Service Area R-7 Funds)
Attachments: 1. NOE - Livorna Park Renovation
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.
To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Advertisement for the Livorna Park Renovation Project, 2615 Miranda Avenue, Alamo
/

RECOMMENDATIONS:
(1) APPROVE the design and bid documents, including the plans and specifications, for the Livorna Park Renovation Project, 2615 Miranda Avenue, Alamo.
(2) AUTHORIZE the Public Works Director, or designee, to solicit bids to be received on or about October 14, 2026, and issue bid addenda, as needed, for clarification of the bid documents, provided the changes do not significantly increase the construction cost estimate.
(3) DIRECT the Clerk of the Board to publish at least 14 calendar days before the bid opening date, the Notice to Contractors in accordance with Public Contract Code Section 22037, inviting bids for this project.
(4) DIRECT the Public Works Director, or designee, to send notices by email or fax and by U.S. Mail to the construction trade journals specified in Public Contract Code Section 22036 at least 15 calendar days before the bid opening.
(5) DETERMINE that this activity is exempt from the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15303(c).

FISCAL IMPACT:
Estimated construction cost $4,000,000.00 (100% Special District Funds from County Service Area R-7 Alamo)

BACKGROUND:
The purpose of this project is to revitalize the aging infrastructure at Livorna Park and replace it with modern, sustainable materials that enhance accessibility, reduce long-term maintenance, and support water conservation. The project’s proposed renovations will replace the existing 8,400 square-foot playground; expand the existing 2,538 square-foot basketball court to a full court by adding approximately 3,074 square-feet and two approximately 4-foot tall concrete retaining walls; repair the bocce court; improve the pavilion by adding perimeter concrete paving and removing its benches and metal railings; improve the main park entrance by rem...