Legislation Details

File #: 26-2378    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 5/26/2026 In control: BOARD OF SUPERVISORS
On agenda: 6/9/2026 Final action:
Title: AWARD and AUTHORIZE the Public Works Director, or designee, to execute a construction contract with Carone and Company, Inc. in the amount of $1,723,095 for the 2026 Crockett and Port Costa Overlays and Curb Ramps, Crockett and Port Costa areas (100% Local Road Funds)
Attachments: 1. Attachment A, 2. Attachment B, 3. Attachment C, 4. Attachment D
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.
To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Construction Contract for the 2026 Crockett and Port Costa Overlays and Curb Ramps.
?Recommendation of the County Administrator ? Recommendation of Board Committee


RECOMMENDATIONS:

(1) APPROVE plans, specifications, and design for the 2026 Crockett and Port Costa Overlays and Curb Ramps. (County Project No. 0672-6U2186) (District V)

(2) DETERMINE that Radius Earthwork Inc. ("Radius"), the lowest monetary bidder, submitted a non-responsive bid by failing to comply with the County's Outreach Program and by failing to submit documentation of Good Faith Effort within two days of bid opening, as required by the project specifications; and REJECT the bid on that basis

(3) DETERMINE that Mission Constructors Inc. ("Mission Constructors"), the second lowest monetary bidder, submitted a non-responsive bid by failing to comply with the County's Outreach Program and by failing to submit documentation of Good Faith Effort within two days of bid opening, as required by the project specifications; and REJECT the bid on that basis

(4) DETERMINE that Carone and Company, Inc. ("Carone"), the third lowest monetary bidder, has complied with the requirements of the County's Outreach Program and has exceeded the Mandatory Subcontracting Minimum for this project, as provided in the project specifications; and FURTHER DETERMINE that Carone has submitted the lowest responsive and responsible bid for the project.

(5) AWARD the construction contract for the above project to Carone in the listed amount ($1,723,095.00) and the unit prices submitted in the bid, and DIRECT that Carone shall present two good and sufficient surety bonds, as indicated below, and that the Public Works Director, or designee, shall prepare the contract.

(6) ORDER that, after the contractor has signed the contract and returned it, together with the bonds as noted below and any required certificates of insurance or ...

Click here for full text