File #: 26-2914    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 6/23/2026 In control: BOARD OF SUPERVISORS
On agenda: 7/7/2026 Final action:
Title: APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a Project Baseline Agreement between Contra Costa County, the California Transportation Commission and the California Department of Transportation to document the project cost, schedule, scope and benefits for the San Pablo Complete Streets/Bay Trail Gap Closure Project, Rodeo and Crockett area. (47% Active Transportation Program, 5% Congressionally Directed Spending, 48% Local Road Funds)
Attachments: 1. Project Baseline Agreement
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.
To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a Project Baseline Agreement between Contra Costa County, the California Transportation Commission and the California Department of Transportation to document the project cost, schedule, scope and benefits for the San Pablo Avenue Complete Streets/Bay Trail Gap Closure Project, Rodeo Crockett area. (47.5% Active Transportation Program (ATP), 4.5% Congressionally Directed Spending, 48% Local Road Funds)
?Recommendation of the County Administrator ? Recommendation of Board Committee


RECOMMENDATIONS:
APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a Project Baseline Agreement between Contra Costa County, the California Transportation Commission (CTC) and the California Department of Transportation (Caltrans) to document the project cost, schedule, scope and benefits for the San Pablo Avenue Complete Streets/Bay Trail Gap Closure Project (Project No. 0662-6R4163), Rodeo Crockett area. (District V)

FISCAL IMPACT:
47.5% Active Transportation Program (ATP) Funds, 4.5% Congressionally Directed Spending Funds, 48% Local Road Funds

BACKGROUND:
The project implements the 2017 Board-approved San Pablo Avenue Complete Streets Study, which established the need and feasibility to incorporate pedestrian and bike infrastructure along the San Pablo Avenue corridor between Pacific Avenue in unincorporated Rodeo and Pomona Street in unincorporated Crockett. The project proposes to restripe the vehicular travel lanes and construct approximately 13,700 linear feet of a separated shared use path between California Street and Pomona Street. Currently, there are not any existing pedestrian and bike infrastructure along this 3-mile segment of San Pablo Avenue.

The project also includes the construction of 2,150 linear feet of new Class II bike lanes between Rodeo Avenue and Parker Avenue. These ...