Legislation Details

File #: 26-3919    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 8/31/2026 In control: BOARD OF SUPERVISORS
On agenda: 9/15/2026 Final action:
Title: Acting as the governing body of the Contra Costa County Flood Control and Water Conservation District, APPROVE and AUTHORIZE the Chief Engineer, or designee, to execute a contract amendment with Kjeldsen, Sinnock & Neudeck, Inc., effective September 29, 2026, to increase the payment limit by $500,000 to a new payment limit of $1,500,000 and extend the term through September 29, 2028, for on-call flood control facility design, Countywide. (100% Flood Control District Funds)
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.
To: The Contra Costa County Flood Control and Water Conservation District Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Contract Amendment with Kjeldsen, Sinnock & Neudeck, Inc., for Professional Engineering Services Relating to Flood Control Facility Design.
Recommendation: Recommendation of the County Administrator
/

RECOMMENDATIONS:
Acting as the governing body of the Contra Costa County Flood Control and Water Conservation District (FCD), APPROVE and AUTHORIZE the Chief Engineer, or designee, to execute a contract amendment with Kjeldsen, Sinnock & Neudeck, Inc., effective September 29, 2026, to increase the payment limit by $500,000 to a new payment limit of $1,500,000 and extend the term through September 29, 2028, for on-call professional engineering services related to flood control facility design, Countywide.

FISCAL IMPACT:
This contract amendment is funded 100% by Flood Control District Funds.

BACKGROUND:
The FCD provides regional flood protection, technical information, hydrology data and education to cities and residents, as well as environmental stewardship for over 70 miles of streams and several detention basins as part of Contra Costa County’s flood protection system. The FCD prepares and reviews designs prepared by others that modify the existing flood protection system and require professional facility design consultation in these efforts. In many cases, the flood protection facility proposed for modification was constructed by the U.S. Army Corps of Engineers or the U.S. Department of Agriculture Natural Resources Conservation Service, which means adherence to their standards, policies, and procedures.

In implementing modifications to the flood control system, the FCD, at times, requires additional temporary professional engineering services, including flood control facility design. For this reason, the FCD entered into an on-call contract with the consultant. Under this contract, the consultant...