File #: RES 2026-37    Version: 1 Name:
Type: Consent Resolution Status: Passed
File created: 1/20/2026 In control: BOARD OF SUPERVISORS
On agenda: 2/10/2026 Final action: 2/10/2026
Title: ADOPT Resolution No, 2026-37 approving and authorizing the Public Works Director, or designee, to fully close a portion of Purdue Avenue on March 2, 2026, from 7:30 a.m. through 5:30 p.m., for the purpose of a utility pole replacement, Kensington area. (No fiscal impact)
To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Approve and Authorize to fully close a portion of Purdue Avenue on March 2, 2026, from 7:30 a.m. through 5:30 p.m., for the purpose of a utility pole replacement, Kensington area.
?Recommendation of the County Administrator ? Recommendation of Board Committee


RECOMMENDATIONS:
ADOPT Resolution approving and authorizing the Public Works Director, or designee, to fully close a portion of Purdue Avenue on March 2, 2026, from 7:30 a.m. through 5:30 p.m., for the purpose of a utility pole replacement, Kensington area. (District I)

FISCAL IMPACT:
No fiscal impact.

BACKGROUND:
Due to the narrow road width of Purdue Avenue at the work site, Pacific Gas & Electric Company (PG&E) has requested the road closure to replace the existing utility pole. There is insufficient road width to set up and operate boom trucks and safely maintain through traffic. Applicant shall follow guidelines set forth by the Public Works Department. This request was previously approved by the Board of Supervisors on December 16, 2025, and in Resolution No. 2025-414. The applicant has submitted a new request due to an unexpected weather event during construction.

CONSEQUENCE OF NEGATIVE ACTION:
Applicant will be unable to close the road to complete planned utility pole replacement.


c: Alex Vazquez-Engineering Services, Marke Smith-Engineering Services, Devon Patel-Engineering Services, Bob Hendry-Engineering Services, Michelle Cordis-Maintenance, Kensington Police Department, Kensington Fire Protection District
















THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board

body
IN THE MATTER OF Approving and authorizing the Public Works Director, or designee, to fully close a portion of Purdue Avenue on March 2, 2026, from 7:30 a.m. through 5:30 p.m., for the purpose of a utility pole replacement, Kensington are...