To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: APPROVE and AUTHORIZE a Progressive Design-Build Contract to Truebeck Construction, Inc., a California Corporation
?Recommendation of the County Administrator ? Recommendation of Board Committee
RECOMMENDATIONS:
AUTHORIZE the use of progressive design build procurement for the Contra Costa Regional Medical Center (CCRMC) Cafeteria Building Upgrades (CBU) project.
APPROVE and AUTHORIZE the Public Works Director, or designee, to sign a Preconstruction Phase progressive design-build contract with Truebeck Construction, Inc. (Truebeck), a California Corporation, in an amount not to exceed $4,266,080.41, including $3,139,500.77 for the base design scope, with $946,579.64 allocated to design an additive alternate and $180,000.00 additional services allowance, as the Design-Build Entity (DBE) for the preconstruction phase of the CCRMC CBU project.
AUTHORIZE the Public Works Director, or designee, to approve final plans, specifications, and design documents necessary to procure a Guaranteed Maximum Price (GMP) from the DBE for the completion of design, permitting, and construction all spaces required to provide in-patient food services to the main hospital, and obtain Health Care Access and Information (HCAI) seismic and non-seismic compliance certifications. Work shall include dietary kitchen, related services, demolition of existing structures as necessary, and related site improvements.
FISCAL IMPACT:
100% Measure X.
The total cost of the base CBU project is estimated at $35,600,000. With an additive alternate to include two cold-shell levels above the base CBU project to add future flexibility, the project cost is estimated at $50,000,000. With progressive design build, an initial preconstruction contract is used to design the project and establish a GMP for the construction project. Once the GMP is established, Public Works will return to the Board of Supervisors re...