To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Approving the twelfth extension for Subdivision Agreement for subdivision SD03-08744, Martinez area.
?Recommendation of the County Administrator ? Recommendation of Board Committee
RECOMMENDATIONS:
ADOPT Resolution approving the twelfth extension of the Subdivision Agreement for subdivision SD03-08744, for a project being developed by Discovery Builders, Inc., as recommended by the Public Works Director, Martinez area. (District V)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
The termination date of the Subdivision Agreement needs to be extended. The developer has not completed the required improvements and has requested more time. (Approximately 0% of the work has been completed to date.) By granting an extension, the County will give the developer more time to complete improvements and keeps the bond current.
CONSEQUENCE OF NEGATIVE ACTION:
The termination date of the Subdivision Agreement will not be extended, and the developer will be in default of the agreement, requiring the County to take legal action against the developer and surety to get the improvements installed, or revert the development to acreage.
C: Larry Gossett-Engineering Services, Kellen O'Connor-Engineering Services, Marke Smith-Engineering Services, Randy Sanders-Design/Construction, Ruben Hernandez -DCD, Discovery Builders, Inc., Lexon Insurance Company, T-6/4/25
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
body
IN THE MATTER OF: Approving the twelfth extension of the Subdivision Agreement for subdivision SD03-08744, for a project being developed by Discovery Builders, Inc., as recommended by the Public Works Director, Martinez area. (District V)
WHEREAS, the Public Works Director having recommended that he be authorized to execute the twelfth agreement extension which extends th...
Click here for full text