Title: ADOPT Resolution No. 2024-388 accepting as complete the contracted work performed by Granite Construction Company for the Storm Damage Repair Project-Alhambra Valley Road at Ferndale, Alhambra Valley Road West of Castro Ranch Road, Bear Creek Road Embankment Repairs, as recommended by the Public Works Director, Briones, Pinole, and Alhambra Valley areas. (69% Local Road Funds, 31% Measure J Return to Source Funds)
Attachments: 1. Recordable Resolution_6211, 2. Signed Resolution 2024-388.pdf

To:                                          Board of Supervisors

From:                                          Warren Lai, Public Works Director/Chief Engineer

Report Title:                     Notice of Completion for the Storm Damage Repair Project-Alhambra Valley Road at Ferndale, Alhambra Valley Road West of Castro Ranch Road, Bear Creek Road Embankment Repairs, Briones, Pinole, and Alhambra Valley areas.

Recommendation of the County Administrator Recommendation of Board Committee

 

RECOMMENDATIONS:

ADOPT Resolution accepting as complete the contracted work performed by Granite Construction Company for the Storm Damage Repair Project-Alhambra Valley Road at Ferndale, Alhambra Valley Road West of Castro Ranch Road, Bear Creek Road Embankment Repairs, as recommended by the Public Works Director, Briones, Pinole, and Alhambra Valley areas. County Project No. 0672-6U6211, County Project No. 0672-6U6225, and County Project No. 0672-6U6226 (Districts I and V).

 

FISCAL IMPACT:

The Project was funded by 69% Local Road Funds, 31% Measure J Return to Source Funds.

 

BACKGROUND:

The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of September 7, 2024.

 

CONSEQUENCE OF NEGATIVE ACTION:

The contractor will not be paid and acceptance notification will not be recorded.