File #: 26-3464    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 7/28/2026 In control: BOARD OF SUPERVISORS
On agenda: 8/11/2026 Final action:
Title: APPROVE the 2025 Walnut Creek Overlays Project contingency fund increase of $295,849 for a new contingency fund total of $548,895, and a new payment limit of $3,079,355, effective August 11, 2026, as recommended by the Public Works Director; Walnut Creek area. (100% Local Road Funds)
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.

To:                                          Board of Supervisors

From:                                          Warren Lai, Public Works Director/Chief Engineer

Report Title:                     APPROVE the contingency fund increase for the 2025 Walnut Creek Overlays Project, Walnut Creek area.

Recommendation of the County Administrator Recommendation of Board Committee

 

RECOMMENDATIONS:

APPROVE the 2025 Walnut Creek Overlays Project contingency fund increase of $295,849.02 for a new contingency fund total of $548,894.97, and a new payment limit of $ 3,079,354.50, effective August 11, 2026, as recommended by the Public Works Director. (District IV)

 

FISCAL IMPACT:

The Project is being funded by 100% Local Road Funds.

 

BACKGROUND:

The contingency fund increase is necessary to compensate the contractor for unforeseen extra work required to complete the project.

 

CONSEQUENCE OF NEGATIVE ACTION:

The lack of approval would prevent successful completion of this contract and prevent payment for the additional work performed by the contractor.