Skip to main content
Contra Costa County Header
File #: 25-2731    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 6/20/2025 In control: BOARD OF SUPERVISORS
On agenda: 7/8/2025 Final action:
Title: APPROVE Budget Amendment No. BDA-25-00078 authorizing the transfer of appropriations from Facility Lifecycle Improvements (0085) to Public Works (0650) for the Schroder Bridge Bearing Pad Replacement for $1,200,000 (Project 6X5240) (100% Measure X Funds)
Attachments: 1. BDA-25-00078
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.

To:                                          Board of Supervisors

From:                                          Warren Lai, Public Works Director/Chief Engineer

Report Title:                     Approve Budget Amendment No. BDA-25-00078 authorizing the transfer of appropriations for the Schroder Bridge Bearing Pad Replacement for $1,200,000 (Project 6X5240) (100% Measure X Funds)

Recommendation of the County Administrator Recommendation of Board Committee

 

RECOMMENDATIONS:

 

APPROVE Budget Amendment No. BDA-25-00078 to transfer appropriations from Facility Lifecycle Improvement, budget unit 0085 to Public Works, budget unit 0650 for the Schroder Bridge Bearing Pad Replacement project (6X5240) in the amount of $1,200,000.

 

FISCAL IMPACT:

100% Measure X funds.

 

 

BACKGROUND:

 

Measure X funds in the amount of $1,200,000 have been allocated for the engineering and construction costs associated with the replacement of existing bearing pads for the Robert I. Schroder Bridge.  Funding was appropriated to Facilities Lifecycle Improvement, budget unit 0085 on 01/31/2025. Public Works Measure X allocations are being consolidated within Public Works budget unit 0650.

 

CONSEQUENCE OF NEGATIVE ACTION:

 

The Schroder Bridge Measure X funding will remain in Facility Lifecycle Improvement budget unit 0085 and will not be consolidated with other Public Works Measure X funding.