To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Accepting completion of private improvements for subdivision SD-08967, Pacheco area
?Recommendation of the County Administrator ? Recommendation of Board Committee
RECOMMENDATIONS:
ADOPT Resolution accepting completion of private improvements per the Subdivision Agreement, and release of cash deposit for subdivision SD05-08967, for a project developed by KB Home South Bay, Inc., as recommended by the Public Works Director, Pacheco area. (100% Developer Fees)
FISCAL IMPACT:
100% developer fees.
BACKGROUND:
The developer has completed the private improvements per the Subdivision Agreement and in accordance with the Title 9 of the County Ordinance Code.
CONSEQUENCE OF NEGATIVE ACTION:
The completion of private improvements will not be accepted. The developer will not receive a refund of the cash deposit, the Subdivision Agreement and performance/maintenance surety bond will not be exonerated, and the billing account will not be liquidated and closed.
Cc: Matt Collins (mcollins@kbhome.com), KB Home South Bay, Inc., Arch Insurance Company, Public Works Department: R. Sanders, C. Lau, C. Halford, D. Patel, C. Herrold, T:5/3/2025
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
IN THE MATTER OF: Accepting completion of private improvements for the Subdivision Agreement and release of cash deposit for faithful performance, subdivision SD05-08967, for a project developed by KB Home South Bay, Inc., as recommended by the Public Works Director, Pacheco area. (District V)
WHEREAS, the Public Works Director has notified this Board that the private improvements in subdivision SD05-08967 have been completed as provided in the Subdivision Agreement with KB Home South Bay, Inc., heretofore approved by this Board in conjunction with the filing of the Subdivision Map.
NOW, THER...
Click here for full text