Legislation Details

File #: 25-1093    Version: 1 Name:
Type: Consent Item Status: Passed
File created: 3/10/2025 In control: BOARD OF SUPERVISORS
On agenda: 3/25/2025 Final action: 3/25/2025
Title: APPROVE and AUTHORIZE the Director of Airports, or designee, to execute a contract amendment with Kimley-Horn and Associates, Inc, effective March 25, 2025, to increase the payment limit by $5,065 to a new payment limit of $642,864, and to extend the term through December 31, 2025, for additional consulting and engineering services, Concord area. (100% Airport Enterprise Fund)

To:                                          Board of Supervisors

From:                                          Greg Baer, Director of Airports

Report Title:                     Increase in Payment Limit and Term Extension on Consulting Services Agreement with Kimley-Horn and Associates

☒Recommendation of the County Administrator ☐ Recommendation of Board Committee

 

RECOMMENDATIONS:

 

APPROVE and AUTHORIZE the Director of Airports, or designee, to execute an amendment to the November 1, 2020, Consulting Services Agreement with Kimley-Horn and Associates, Inc., under which Kimley-Horn provides design and construction management services for the construction of security upgrades at Buchanan Field Airport, to increase the payment limit by $5,065 to a new payment limit of $642,864 and extend the contract term through December 31, 2025.

 

 

FISCAL IMPACT:

 

The increased cost is fully funded by the Airport Enterprise Fund.

 

 

BACKGROUND:

 

Under a Consulting Services Agreement (CSA) dated November 1, 2020, Kimley-Horn, Associates Inc., (Kimley-Horn) prepared the design and performed construction management tasks for the security upgrades project at Buchanan Field Airport.  The CSA is being amended to:

1.                     Extended the term of the contract to December 31, 2025, to give Kimley-Horn time to complete the Federal Aviation Administration (FAA) project close out documents and additional required services, and

2.                     To increase the contract amount by $5,065 to a new contract limit of $642,864, in order to complete additional consulting and engineering services needed for the punch-list phase of the project.

 

 

CONSEQUENCE OF NEGATIVE ACTION:

 

If the CSA amendment is not approved, Kimley-Horn will not be able to complete the final tasks needed to close out the project with the FAA.