Contra Costa County Header
File #: 24-3704    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 10/22/2024 In control: BOARD OF SUPERVISORS
On agenda: 11/5/2024 Final action:
Title: APPROVE the Danville Boulevard-Orchard Court Improvements Project contingency fund increase of $350,000 for a new contingency fund total of $626,007, and a new payment limit of $3,386,077, effective November 5, 2024, as recommended by the Public Works Director, Alamo area. (66% Highway Safety Improvement Program Grant Funds, 33% Measure J Funds, and 1% Local Road Funds)
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.

To:                                          Board of Supervisors

From:                                          Warren Lai, Public Works Director/Chief Engineer

Report Title:                     APPROVE the contingency fund increase for the Danville Boulevard-Orchard Court Improvements Project, Alamo area.

Recommendation of the County Administrator Recommendation of Board Committee

 

RECOMMENDATIONS:

 

APPROVE the Danville Boulevard-Orchard Court Improvements Project contingency fund increase of $350,000.00 for a new contingency fund total of $626,007.00, and a new payment limit of $3,386,077.00, effective November 5, 2024, as recommended by the Public Works Director, Alamo area. (County Project No.: 0662-6R4128), (Federal Project No.: HSIPL-5928(140))(District II).

 

FISCAL IMPACT:

 

The Project is funded by 66% Highway Safety Improvement Program Grant Funds, 33% Measure J Funds, and 1% Local Road Funds.

 

BACKGROUND:

 

The contingency fund increase is necessary to compensate the contractor for unforeseen extra work required to complete the project and associated overhead costs.

 

CONSEQUENCE OF NEGATIVE ACTION:

 

The lack of approval would prevent successful completion of this contract and prevent payment for the additional work performed by the contractor.