Title: APPROVE and AUTHORIZE the Public Works Director, or designee, to award a construction contract in the amount of $4,500,000 with Penkor General Contractors, Inc., for Demolition of Old Juvenile Hall Project, Martinez area. (65% State Fund, 35% General Fund)
Attachments: 1. Notice of Exemption (Old Juvenile Hall)
To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: AWARD construction contract to Penkor General Contractors, Inc. for the Demolition of the Old Juvenile Hall project
?Recommendation of the County Administrator ? Recommendation of Board Committee


RECOMMENDATIONS:
(1) APPROVE the design and bid documents, including the plans and specifications, for the Demolition of Old Juvenile Hall Project at 202 Glacier Drive, Martinez.

(2) FIND that the bid submitted by Penkor General Contractors, Inc., (dba Penkor Wrecking) is the lowest responsive and responsible bid; DETERMINE that said bid complies with all requirements of the Project specifications, including the County's Outreach Program; and WAIVE any minor irregularities in said bid.

(3) DIRECT that, as a condition of contract award, Penkor General Contractors, Inc. and its subcontractors shall execute a Project Labor Agreement for the Project.

(4) AWARD the construction contract to Penkor General Contractors, Inc. in the amount of $4,500,000 and DIRECT the Public Works Director, or designee, to prepare the contract.

(5) DIRECT that Penkor General Contractors, Inc. shall submit two good and sufficient security bonds (performance and payment bonds) in the amount of $4,500,000 each.

(6) ORDER that, after Penkor General Contractors, Inc. has signed the contract and returned it, together with the bonds, evidence of insurance, and other required documents, and the Public Works Director has reviewed and found them to be sufficient, the Public Works Director, or designee, is authorized to sign the contract for this Board.

(7) ORDER that, in accordance with the Project specification and upon signature of the construction contract by the Public Works Director, or designee, any bid bonds posted by the bidders are exonerated and any checks or cash submitted for bid security shall be returned.

(8) AUTHORIZE the Public Works Director, or designee, to sign any escrow agreemen...

Click here for full text