Skip to main content
Contra Costa County Header
File #: 25-3081    Version: 1 Name:
Type: Consent Item Status: Passed
File created: 7/24/2025 In control: BOARD OF SUPERVISORS
On agenda: 8/5/2025 Final action: 8/5/2025
Title: APPROVE and AUTHORIZE the Chief Information Officer to execute a contract amendment with Aviat U.S., Inc., with no change to the payment limit, to extend the term through December 31, 2025, for continued radio and microwave equipment installation services. (100% User Departments)
To: Board of Supervisors
From: Marc Shorr, Information Technology Director
Report Title: Contract Amendment with Aviat U.S., Inc.
?Recommendation of the County Administrator ? Recommendation of Board Committee


RECOMMENDATIONS:

APPROVE and AUTHORIZE the Chief Information Officer to execute a contract amendment with Aviat U.S., Inc., with no change to the payment limit, to extend the term through December 31, 2025, for continued radio and microwave equipment installation services.

FISCAL IMPACT:

The cost for this contract is included in the Department's FY25/26 budget. 100% User Departments.

BACKGROUND:

The Department of Information Technology maintains and operates the County's primary data center providing critical services to the County that must be continuously available in the event of a natural disaster including earthquakes, fire and floods. In late 2022, the County started researching possible locations that could serve as a disaster recovery site as we did not currently have a viable disaster recovery center. After taking into consideration many different factors such as a low monthly fixed cost, and guaranteed 100% uptime, the County selected Nautilus Data Technologies, Inc. which is built on a floating barge that is permanently docked at the Port of Stockton in San Joaquin County. The County is now in the process of completing a connection to the site to establish data transfer for systemwide back-up and restoration.

The current Aviat contract has a payment limit of $270,000 for a term of September 1, 2024, to April 30, 2025, and was approved by the Board of Supervisors on September 10, 2024.

The extension of this contract is warranted due to unforeseen delays in the delivery of critical equipment. The extended lead times for procurement significantly impacted the project schedule and prevented timely commencement of engineering activities. These delays were beyond the County's and the Contractor's control and necessitate additional time to co...

Click here for full text