To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Approving the tenth extension of the Subdivision Agreement for subdivision SD91-07553, Alamo area.
?Recommendation of the County Administrator ? Recommendation of Board Committee
RECOMMENDATIONS:
ADOPT Resolution approving the tenth extension of the Subdivision Agreement for subdivision SD91-07553, for a project being developed by Alamo Land Investors, LLC and Alamo 37, LLC, as recommended by the Public Works Director, Alamo area. (District II)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
The termination date of the Subdivision Agreement needs to be extended. The developer has not completed the required improvements and has requested more time. (Approximately 0% of the work has been completed to date.) By granting an extension, the County will give the developer more time to complete improvements and keeps the bond current.
CONSEQUENCE OF NEGATIVE ACTION:
The termination date of the Subdivision Agreement will not be extended and the developer will be in default of the agreement, requiring the County to take legal action against the developer and surety to get the improvements installed, or revert the development to acreage.
c: Jocelyn LaRocque-Engineering Services, Kellen O'Connor-Engineering Services, Marke Smith-Engineering Services, Randy Sanders-Design/Construction, Ruben Hernandez -DCD, Alamo Land Investor, LLC and Alamo 37 LLC, Lexon Insurance Company
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
IN THE MATTER OF: Approving the tenth extension of the Subdivision Agreement for subdivision SD91-07553, for a project being developed by Alamo Land Investors, LLC and Alamo 37, LLC, as recommended by the Public Works Director, Alamo area. (District II)
WHEREAS, the Public Works Director having recommended that he be authorized to execute the tenth agreement exte...
Click here for full text