To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Accepting completion of improvements for the Subdivision Agreement, without the need of a warranty period and release of cash deposit for faithful performance for minor subdivision MS19-00003, Walnut Creek area.
Recommendation: Recommendation of the County Administrator
/
RECOMMENDATIONS:
ADOPT Resolution accepting completion of improvements for the Subdivision Agreement, without the need of a warranty period and release of cash deposit for faithful performance, for minor subdivision MS19-00003, for a project developed by HD 2063 Walnut Creek LLC, as recommended by the Public Works Director, Walnut Creek area. (District II)
FISCAL IMPACT:
100% Developer Fees.
BACKGROUND:
The developer has completed the improvements per the Subdivision Agreement, and in accordance with the Title 9 of the County Ordinance Code.
CONSEQUENCE OF NEGATIVE ACTION:
The developer will not receive a refund of the cash deposit, the Subdivision Agreement and surety bond will not be exonerated, and completion of private improvements will not be accepted.
C: J. LaRocque, Engineering Services, A. Vazquez, Engineering Services, J. Ma, Engineering Services, J. Hernandez, Engineering Services, T. Shepherd, Design/Construction Div, C. Halford, Mapping, W. Gardizi, Finance, HD 2063 Walnut Creek LLC, Arch Insurance Company, T. April 6, 2027
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
body
IN THE MATTER OF: Accepting completion of improvements for the Subdivision Agreement, without the need of a warranty period and release of cash deposit for faithful performance, for minor subdivision MS19-00003, for a project developed by HD 2063 Walnut Creek LLC, as recommended by the Public Works Director, Walnut Creek area. (District II)
WHEREAS, the Public Works Director has notified this Board tha...