To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Approve and Authorize to fully close a portion of Franciscan Way, on April 17, 2024, from 7:30 a.m. through 5:30 p.m., Kensington area.
?Recommendation of the County Administrator ? Recommendation of Board Committee
RECOMMENDATIONS:
ADOPT Resolution approving and authorizing the Public Works Director, or designee, to fully close a portion of Franciscan Way, between Anson Way and Eureka Avenue, on April 17, 2024, from 7:30 a.m. through 5:30 p.m., for the purpose of utility pole replacement, Kensington area. (District I)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
Pacific Gas and Electric Company shall follow guidelines set forth by the Public Works Department. Pacific Gas and Electric Company is requesting a road closure to replace a utility pole. The construction team indicated that a road closure is necessary for the requested work to be done safely due to the narrow road.
CONSEQUENCE OF NEGATIVE ACTION:
Applicant will be unable to close the road for planned activities.
c: Larry Gossett-Engineering Services, Kellen O'Connor-Engineering Services, Bob Hendry, Engineering Services, Marke Smith, Engineering Services, Devon Patel, Engineering Services, Chris Lau, Maintenance, Kensington Police Department & Fire Protection District
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
body
IN THE MATTER OF: Approving and Authorizing the Public Works Director, or designee, to fully close a portion of Franciscan Way, between Anson Way and Eureka Avenue, on April 17, 2024, from 7:30 a.m. through 5:30 p.m., for the purpose of utility pole replacement, Kensington area. (District I)
RC24-18
NOW, THEREFORE, BE IT RESOLVED that permission is granted to Pacific Gas and Electric Company to fully close a portion of Franciscan Way, between Anson Way a...