File #: RES 2025-273    Version: 1 Name:
Type: Consent Resolution Status: Passed
File created: 7/22/2025 In control: BOARD OF SUPERVISORS
On agenda: 8/12/2025 Final action: 8/12/2025
Title: ADOPT Resolution No. 2025-273 approving and authorizing the Public Works Director, or designee, to fully close a portion of Flora Avenue between Boulevard Way and Sally Lane, on August 25, 2025, through October 15, 2025, from 7:00 a.m. through 5:00 p.m., for the purpose of installing a storm drain trash capture device, Walnut Creek area. (No fiscal impact)
To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Approve and Authorize to fully close a portion of Flora Avenue between Boulevard Way and Sally Lane, on August 25, 2025, through October 15, 2025, from 7:00 a.m. through 5:00 p.m., for the purpose of installing a storm drain trash capture device, Walnut Creek area.
?Recommendation of the County Administrator ? Recommendation of Board Committee


RECOMMENDATIONS:
ADOPT Resolution approving and authorizing the Public Works Director, or designee, to fully close a portion of Flora Avenue, between Boulevard Way and Sally Lane, on August 25, 2025, through October 15, 2025, from 7:00 a.m. through 5:00 p.m., for the purpose of installing a storm drain trash capture device, Walnut Creek area. (District II)

FISCAL IMPACT:
No fiscal impact.

BACKGROUND:
This road closure is necessary for the Saranap Trash Capture Installation, County Project No. 7517-6W7080. The size of the excavation within the road does not allow W.R. Forde Associates, Inc. to safely maintain through traffic during construction. The applicant will allow local and emergency traffic through the site during working hours. The excavation will be covered with traffic rated steel plates during non-working hours and the road reopened to through traffic. The applicant shall follow the guidelines set forth by the Public Works Department.

CONSEQUENCE OF NEGATIVE ACTION:
Applicant will be unable to close the road to complete the Saranap Trash Capture Installation project.


c: Kellen O'Connor-Engineering Services, Marke Smith-Engineering Services, Devon Patel-Engineering Services, Bob Hendry-Engineering Services, Chris Lau-Maintenance, CHP, Sheriff-Patrol Div. Commander














THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board

body
IN THE MATTER OF: Approving and Authorizing the Public Works Director, or designee, to fully close ...

Click here for full text