To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Approve and Authorize to fully close a portion of Flora Avenue between Boulevard Way and Sally Lane, on August 25, 2025, through October 15, 2025, from 7:00 a.m. through 5:00 p.m., for the purpose of installing a storm drain trash capture device, Walnut Creek area.
?Recommendation of the County Administrator ? Recommendation of Board Committee
RECOMMENDATIONS:
ADOPT Resolution approving and authorizing the Public Works Director, or designee, to fully close a portion of Flora Avenue, between Boulevard Way and Sally Lane, on August 25, 2025, through October 15, 2025, from 7:00 a.m. through 5:00 p.m., for the purpose of installing a storm drain trash capture device, Walnut Creek area. (District II)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
This road closure is necessary for the Saranap Trash Capture Installation, County Project No. 7517-6W7080. The size of the excavation within the road does not allow W.R. Forde Associates, Inc. to safely maintain through traffic during construction. The applicant will allow local and emergency traffic through the site during working hours. The excavation will be covered with traffic rated steel plates during non-working hours and the road reopened to through traffic. The applicant shall follow the guidelines set forth by the Public Works Department.
CONSEQUENCE OF NEGATIVE ACTION:
Applicant will be unable to close the road to complete the Saranap Trash Capture Installation project.
c: Kellen O'Connor-Engineering Services, Marke Smith-Engineering Services, Devon Patel-Engineering Services, Bob Hendry-Engineering Services, Chris Lau-Maintenance, CHP, Sheriff-Patrol Div. Commander
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
body
IN THE MATTER OF: Approving and Authorizing the Public Works Director, or designee, to fully close ...