Legislation Details

File #: 26-3492    Version: 1 Name:
Type: Discussion Item Status: Agenda Ready
File created: 8/6/2026 In control: Transitional Community Advisory Board
On agenda: 8/10/2026 Final action:
Title: RECEIVE update on the Lead Entity Request for Qualifications (RFQ) procurement process
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.

Meeting Date:                                          August 10, 2026

Subject:                                           Lead Entity RFQ Update

Submitted For:                     Transitional Community Advisory Body

Presenter:                                          ORESJ Staff

Contact:                                          Jessica Travenia, jessica.travenia@oresj.cccounty.us <mailto:jessica.travenia@oresj.cccounty.us>

_____________________________________________________________________________

Information:

TCAB will receive updates on the RFQ procurement process.

Referral History and Update:

The Request for Qualifications (RFQ #0038) closed on August 6, 2026.

Staff have begun the procurement review process consistent with County procurement requirements.

Staff will provide available updates regarding:

Procurement Milestones

-                     Questions & Answers published on BidNet on July 15, 2026.

-                     Proposal submission period closed on August 6, 2026.

-                     Five-member Review Panel confirmed

-                     Panel Orientation completed on August 5, 2026.

-                     Proposal Evaluation Period is August 7 - September 7, 2026.

-                     Review Panel is using the published evaluation rubric.

-                     Qualified vendors will be notified on September 8, 2026.

-                     Qualified vendors advance to Phase Two

-                     Lead Entity Bid (Phase Two) process begins on September 22, 2026.

-                     Interviews will be scheduled.

-                     Final recommendation proceeds through Equity Committee (November 2026) and Board of Supervisors (December 2026)

 

Recommendation(s) / Next Step(s):

Receive update on RFQ process.