Legislation Details

File #: 26-4935    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 10/28/2026 In control: BOARD OF SUPERVISORS
On agenda: 11/17/2026 Final action:
Title: Acting as the governing body of the Flood Control and Water Conservation District, APPROVE the Wildcat Fish Passage Implementation Project contingency fund increase of $1,240,000 for a new contingency fund total of $1,645,148 with Good Fellow Bros. California, LLC, and a new payment limit of $5,696,627, effective November 17, 2026, as recommended by the Chief Engineer, Flood Control and Water Conservation District, North Richmond area. (22% U.S. Environmental Protection Agency Grant, 31% Department of Water Recourses Grant, and 47% Local Funds)
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.

To:                                          Board of Supervisors

From:                                          Warren Lai, Public Works Director/Chief Engineer

Report Title:                      APPROVE the contingency fund increase for the Wildcat Fish Passage Implementation Project, North Richmond area.

Recommendation: Recommendation of the County Administrator

 

RECOMMENDATIONS:

Acting as the governing body of the Flood Control and Water Conservation District, APPROVE the Wildcat Fish Passage Implementation Project contingency fund increase of $1,240,000 for a new contingency fund total of $1,645,147.90 with Good Fellow Bros. California LLC, and a new payment limit of $5,696,626.90, effective November 17, 2026, as recommended by the Chief Engineer, Flood Control and Water Conservation District, North Richmond area. [County Project No. 7505-6F8101] (District 1)

 

FISCAL IMPACT:

The Project is being funded by 22.1% U.S. Environmental Protection Agency Grant, 30.5% Department of Water Recourses Grant, and 47.4% Local Funds.

 

BACKGROUND:

The contingency fund increase is necessary to compensate the contractor for unforeseen extra work required to complete the project.

 

CONSEQUENCE OF NEGATIVE ACTION:

The lack of approval would prevent successful completion of this contract and prevent payment for the additional work performed by the contractor.