To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Notice of Completion for the San Pablo Dam Road and Bailey Road Signal Hardware Upgrades Project, Bay Point and El Sobrante areas.
☒Recommendation of the County Administrator ☐ Recommendation of Board Committee
RECOMMENDATIONS:
ADOPT Resolution accepting as complete the contracted work performed by DC Electric Group, Inc. for the San Pablo Dam Road and Bailey Road Signal Hardware Upgrades Project, as recommended by the Public Works Director, Bay Point and El Sobrante areas. County Project No. 0662-6R4139, State Project No. HSIPSL 5928(162) (Districts I, V)
FISCAL IMPACT:
The Project was funded by 92% Highway Safety Improvement Program (HSIP), 8% Local Road Funds.
BACKGROUND:
The Public Works Director reports that said work has been inspected and complies with the approved plans, special provisions and standard specifications and recommends its acceptance as complete as of September 19, 2024.
CONSEQUENCE OF NEGATIVE ACTION:
The contractor will not be paid and acceptance notification will not be recorded.