Skip to main content
Contra Costa County Header
File #: 26-395    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 1/15/2026 In control: BOARD OF SUPERVISORS
On agenda: 2/3/2026 Final action:
Title: Acting as the governing body of the Contra Costa County Flood Control and Water Conservation District, APPROVE and AUTHORIZE the Chief Engineer, or designee, to execute a funding agreement with the City of Richmond, effective February 4, 2026, to pay the District $780,000 in City funds for the Wildcat Creek Fish Passage Implementation Project, North Richmond area. (34% California Department of Water Resources Funds, 28% US Environmental Protection Agency Funds, 38% other State and Local Grant Funds)
Attachments: 1. Funding Agreement with City of Richmond for Wildcat Creek Fish Passage Implementation Project
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.
To: The Contra Costa County Flood Control and Water Conservation District Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Funding Agreement with the City of Richmond for the Wildcat Creek Fish Passage Implementation Project.
?Recommendation of the County Administrator ? Recommendation of Board Committee


RECOMMENDATIONS:
Acting as the governing body of the Contra Costa County Flood Control and Water Conservation District (Flood Control District), APPROVE and AUTHORIZE the Chief Engineer, or designee, to execute the Funding Agreement with the City of Richmond (City), effective February 4, 2026, to pay the District $780,000 in City funds for the Wildcat Creek Fish Passage Implementation Project (WCFPI Project).

FISCAL IMPACT:
The Funding Agreement requires the City of Richmond to contribute $780,000 toward the cost to plan, design, construct, and implement the WCFPI Project (Project No. 7505-6F8106). Remaining WCFPI Project costs are funded by the California Department of Water Resources Urban Streams Restoration Program and the US Environmental Protection Agency San Francisco Bay Water Quality Improvement Fund (Project No. 7505-6F8101 through 7505-6F8104).

BACKGROUND:
The Flood Control District plans to implement the WCFPI Project, which includes improving fish passage in Wildcat Creek, widening a sedimentation basin, and modifying a flood control structure to reduce flood risk to nearby neighborhoods. The WCFPI Project is located in the North Richmond area. The City and the Flood Control District have discussed the WCFPI Project improvements, and the City has determined that the WCFPI Project offers benefits and wishes to contribute to its costs.

The Funding Agreement requires the City to provide the District $780,000 in City funds for the WCFPI Project within 90 days after the effective date of the agreement. Any amount not used by the District for the planning, design, construction, and implementation of the projec...