To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Accepting completion of private improvements for the Subdivision Agreement for minor subdivision MS23-00014, Alamo area.
?Recommendation of the County Administrator ? Recommendation of Board Committee
RECOMMENDATIONS:
ADOPT Resolution accepting completion of private improvements for the Subdivision Agreement and release of cash deposit for faithful performance for minor subdivision MS23-00014 for a project developed by Zackary & Mariela Onisko, as recommended by the Public Works Director, Alamo area. (District II)
FISCAL IMPACT:
100% Developer Fees
BACKGROUND:
The developer has completed the private improvements per the Subdivision Agreement, and in accordance with the Title 9 of the County Ordinance Code.
CONSEQUENCE OF NEGATIVE ACTION:
The developer will not receive a refund of the cash deposit, the Subdivision Agreement and surety bond will not be exonerated, and completion of private improvements will not be accepted.
c: A. Vazquez- Engineering Services, J. Hernandez- Engineering Services, T. Shepherd-Design/Construction Div., C. Halford-Mapping, C. Herrold-Finance, Zackery & Mariela Onisko, Old Republic Surety Company, T. July 13, 2026
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
body
IN THE MATTER OF: Accepting completion of private improvements for the Subdivision Agreement and release of cash deposit for faithful performance for minor subdivision MS23-00014 for a project developed by Zackary & Mariela Onisko, as recommended by the Public Works Director, Alamo area. (District II)
WHEREAS, the Public Works Director has notified this Board that the private improvements in minor subdivision MS23-00014 have been completed as provided in the Subdivision Agreement with Zackary & Mariela Onisko, heretofore approved by this Board in conjunction with the f...
Click here for full text