File #: 26-2133    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 5/5/2026 In control: BOARD OF SUPERVISORS
On agenda: 5/19/2026 Final action:
Title: AWARD and AUTHORIZE the Chief Engineer, or designee, to execute a construction contract with Kerex Engineering, Inc. in the amount of $458,150 for the Pinole Creek Bank Erosion Repair, Pinole area (100% Flood Control Funds)
Attachments: 1. Letter to Gaub Pinole
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.
To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Construction Contract for the Pinole Creek Bank Erosion Repair.
?Recommendation of the County Administrator ? Recommendation of Board Committee


RECOMMENDATIONS:
(1) APPROVE plans, specifications, and design for the Pinole Creek Bank Erosion Repair. (County Project No. 7532-6D9N03) (District I)
(2) DETERMINE that Gaub Trucking Corporation ("Gaub"), the lowest monetary bidder, submitted a non-responsive bid by failing to comply with the requirements of the County's Outreach Program for this project, as provided in the project specifications; and REJECT the bid on that basis
(3) DETERMINE that Kerex Engineering, Inc. ("Kerex"), the second lowest monetary bidder, has complied with the requirements of the County's Outreach Program and has exceeded the Mandatory Subcontracting Minimum for this project, as provided in the project specifications; and FURTHER DETERMINE that Kerex has submitted the lowest responsive and responsible bid for the project.
(4) AWARD the construction contract for the above project to Kerex in the listed amount ($458,150.00) and the unit prices submitted in the bid, and DIRECT that Kerex shall present two good and sufficient surety bonds, as indicated below, and that the Chief Engineer, or designee, shall prepare the contract.
(5) ORDER that, after the contractor has signed the contract and returned it, together with the bonds as noted below and any required certificates of insurance or other required documents, and the Chief Engineer has reviewed and found them to be sufficient, the Chief Engineer, or designee, is authorized to sign the contract for this Board
(6) ORDER that, in accordance with the project specifications and/or upon signature of the contract by the Chief Engineer, or designee, bid bonds posted by the bidders are to be exonerated and any checks or cash submitted for security shall be returned
(7) ORDER that, the Chief Engineer, or d...

Click here for full text