Title: MONTECITO DEVELOPMENT CO. LLC (Applicant) and CONTRA COSTA COUNTY (Owner), County File# DP21-3022: the applicant is requesting approval of a Development Plan Permit to construct a 223,145 square foot warehouse building with associated off-site improvements (i.e., roadway improvements, sidewalks, curbs, gutters, landscaping, utility connections, and traffic calming improvements), driveway connections to both Marsh Drive and Sally Ride Drive, a new intersection at Marsh Drive/Sally Ride Drive (north), lane separation and other improvements related to a proposed separated bike facility on Marsh Drive and removal of one tree. The proposed project site is approximately 16-acres located on the western portion of Buchanan Field Airport between Marsh Drive and Sally Ride Drive, in the Pacheco area. In accordance with Section 15021 of the California Environmental Quality Act (CEQA) Guidelines, Contra Costa County, as lead agency, has prepared a Draft Environmental Impact Report (DEIR). A public...
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.
Project Title:
FSRE Industrial Concord Project
County File:
DP21-3022
Applicant/Owner:
FSRE Industrial Concord Company, LLC./Contra Costa County
General Plan/Zoning:
Public and Semi-Public/Unrestricted
Site Address/Location:
Approximately 16 acres of undeveloped land (Assessor's Parcel Number 125-010-023) on Buchanan Field Airport's western edge, between Marsh Drive and Sally Ride Drive.
California Environmental Quality Act (CEQA) Status:
Section 15087: Public Review of Draft Environmental Impact Report (DEIR)
Project Planner:
Jamar Stamps, AICP, Principal Planner, (925) 655-2917
Staff Recommendation(s):
OPEN the public hearing and ACCEPT public comments on the adequacy of the DEIR.

I. PROJECT SUMMARY

The applicant is requesting approval of a Development Plan (proposed project) to allow the following:

* Construction of a single-story concrete tilt-up logistics warehouse totaling 223,145 square feet, which would include approximately 213,962 square feet of warehouse space and approximately 9,183 square feet of ancillary office space;

* Development of approximately 3.11 acres of on-site stormwater treatment areas;

* Construction of 223 auto parking stalls, including seven American with Disabilities Act (ADA) compliant stalls; 38 trailer parking stalls; 24 bicycle parking spaces (12 short-term and 12 long-term); 38 trailer stalls; and 36 truck docks;

* Construction of off-site improvements, such as roadway improvements, sidewalks, curbs, gutters, landscaping, utility connections, traffic calming improvements, driveway connections to both Marsh Drive and Sally Ride Drive, a new signalized intersection at Marsh Drive/Sally Ride Drive (north), and lane separation and other improvements related to a proposed separated bike facility on Marsh Drive;

* Removal of one tree;

* Development of landscaping, security lighting, and fencing; and

* As part of the General Plan Amendment, reclassification of Sally Ride Drive from a future Arterial to a Collector.