To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Ratify the prior decision to fully close a portion of Fourth Avenue South on September 5, 2024, from 8:00 a.m. through 4:00 p.m., Pacheco area.
?Recommendation of the County Administrator ? Recommendation of Board Committee
RECOMMENDATIONS:
ADOPT Resolution ratifying the prior decision of the Public Works Director, or designee, to fully close a portion of Fourth Avenue South between High Street and Ironwood Drive, on September 5, 2024, from 8:00 a.m. through 4:00 p.m., for the purpose of setting up and operating a crane in the road right-of-way to deliver an accessory dwelling unit (ADU) to the property, Pacheco area. (District V)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
This item was previously approved by the Board on July 23, 2024. The applicant has provided a revised closure date due to a schedule change. The applicant has requested the road closure to park trucks and stage the placement of an ADU on the subject property. The closure will facilitate the setup and operation of a crane from the roadway to place the ADU on the property. The closure is necessary to guarantee access to the subject property and to ensure traffic safety while operating the crane. The applicant shall follow guidelines set forth by the Public Works Department.
CONSEQUENCE OF NEGATIVE ACTION:
Applicant will be unable to close the road for planned activities.
:Larry Gossett-Engineering Services, Kellen O'Connor-Engineering Services, Bob Hendry-Engineering Services, Devon Patel- Engineering Services, Marke Smith-Engineering Services, Chris Lau-Maintenance, CHP, Sheriff- Patrol Division Commander
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
body
IN THE MATTER OF Ratifying the prior decision of the Public Works Director, or designee, to fully close a portion of Fourth Avenue South b...