To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Accepting completion of improvements for subdivision SD21-09588, for a project developed by Loreto Residential, LLC, Bay Point area.
☒Recommendation of the County Administrator ☐ Recommendation of Board Committee

RECOMMENDATIONS:
ADOPT Resolution accepting completion of improvements for subdivision SD21-09588, for a project developed by Loreto Residential, LLC, as recommended by the Public Works Director, Bay Point area. (District V)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
The developer has completed the improvements per the Subdivision Agreement, and in accordance with the Title 9 of the County Ordinance Code.
CONSEQUENCE OF NEGATIVE ACTION:
The completion of improvements will not be accepted as complete, and the warranty period will not begin.
c: Jocelyn LaRocque-Engineering Services, Alex Vazquez-Engineering Services, Jesse Ma-Engineering Services, Anthony DiSilvestre-Engineering Services, Renee Hutchins-Records, Eric Sanders-Design/Construction, Michelle Cordis-Maintenance, Alex Martinez-Surveys, Allan Ruyters-Surveys, Chris Hallford-Mapping, Rochelle Johnson-Special Districts, Jessi Duffy-Special Districts, Ciara Herrold-Finance, Loreto Residential, LLC, Lexon Insurance Company