To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Approve and Authorize to fully close a portion of Alexander Street, on April 13, 2025, from 8:00 a.m. through 5:00 p.m., for the purpose of replacing two utility poles, overhead lines and a transformer, Crockett area.
?Recommendation of the County Administrator ? Recommendation of Board Committee
RECOMMENDATIONS:
ADOPT Resolution approving and authorizing the Public Works Director, or designee, to fully close a portion of Alexander Street between Alhambra Street and 271 Alexander Street, on April 13, 2025, from 8:00 a.m. through 5:00 p.m., for the purpose of replacing two utility poles, overhead lines and a transformer, Crockett area. (District V)
FISCAL IMPACT:
No fiscal impact.
BACKGROUND:
Due to the narrow road width of Alexander Street at the work site, Pacific Gas & Electric Company (PG&E) has requested the road closure to replace two existing utility poles, overhead lines and a transformer. There is insufficient road width to setup and operate boom trucks and safely maintain through traffic. Applicant shall follow guidelines set forth by the Public Works Department.
CONSEQUENCE OF NEGATIVE ACTION:
Applicant will be unable to close the road to complete planned utility pole replacement.
c: Kellen O'Connor-Engineering Services, Marke Smith-Engineering Services, Devon Patel-Engineering Services, Bob Hendry-Engineering Services, Chris Lau-Maintenance, CHP, Sheriff's Department & Crockett-Carquinez Fire Department
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board
body
IN THE MATTER OF: Approving and Authorizing the Public Works Director, or designee, to fully close a portion of Alexander Street, between Alhambra Street and 271 Alexander Street, on April 13, 2025, from 8:00 a.m. through 5:00 p.m., for the purpose of replacing two utility poles, overhead lines and...
Click here for full text