Legislation Details

File #: RES 2026-290    Version: 1 Name:
Type: Consent Resolution Status: Agenda Ready
File created: 6/24/2026 In control: BOARD OF SUPERVISORS
On agenda: 7/14/2026 Final action:
Title: ADOPT Resolution No. 2026-290 approving and authorizing the Public Works Director, or designee, to fully close a portion of Berkeley Park Boulevard, between Ocean View Avenue and Lexington Road, on July 16, 2026, from 8:30 a.m. through 4:00 p.m., for the purpose of a utility pole replacement, Kensington area. (No fiscal impact)
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
No records to display.
To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Approve and Authorize to fully close a portion of Berkeley Park Boulevard, on July 16, 2026, from 8:30 a.m. through 4:00 p.m., for the purpose of a utility pole replacement, Kensington area.
?Recommendation of the County Administrator ? Recommendation of Board Committee


RECOMMENDATIONS:
ADOPT Resolution approving and authorizing the Public Works Director, or designee, to fully close a portion of Berkeley Park Boulevard, between Ocean View Avenue and Lexington Road, on July 16, 2026, from 8:30 a.m. through 4:00 p.m., for the purpose of replacing a utility pole, Kensington area. (District I)

FISCAL IMPACT:
No fiscal impact.

BACKGROUND:
Due to the narrow road width of Berkeley Park Boulevard at the work site, Pacific Gas & Electric Company (PG&E) has requested the road closure to replace the existing utility pole. There is insufficient road width to setup and operate boom trucks and safely maintain through traffic. Applicant shall follow guidelines set forth by the Public Works Department. This request was previously approved by the Board of Supervisors on June 9, 2026, and in Resolution No. 2026-203. The applicant has submitted a new request due to a revision in construction scheduling.

CONSEQUENCE OF NEGATIVE ACTION:
Due to the narrow road width of Berkeley Park Boulevard at the work site, Pacific Gas & Electric Company (PG&E) has requested the road closure to replace the existing utility pole. There is insufficient road width to setup and operate boom trucks and safely maintain through traffic. Applicant shall follow guidelines set forth by the Public Works Department. This request was previously approved by the Board of Supervisors on June 9, 2026, and in Resolution No. 2026-203. The applicant has submitted a new request due to a revision in construction scheduling.


c: Alex Vazquez-Engineering Services, Marke Smith-Engineering Services, Michelle Cordis-Maintena...