Contra Costa County Header
File #: RES 2025-06    Version: 1 Name:
Type: Consent Resolution Status: Passed
File created: 12/16/2024 In control: BOARD OF SUPERVISORS
On agenda: 1/14/2025 Final action: 1/14/2025
Title: APPROVE and AUTHORIZE the Public Works Director, or designee, to execute a Funding Agreement between Contra Costa County and the East Bay Regional Park District for the design and construction of the Clark Road Resurfacing Project, El Sobrante area. (33% East Bay Regional Park District Funds and 67% Local Road Funds)
To: Board of Supervisors
From: Warren Lai, Public Works Director/Chief Engineer
Report Title: Approve and Authorize to fully close a portion of Arlington Court on January 16, 2025, from 7:00 a.m. through 5:00 p.m., for the purpose of an utility pole replacement, Kensington area.
?Recommendation of the County Administrator ? Recommendation of Board Committee


RECOMMENDATIONS:
ADOPT Resolution approving and authorizing the Public Works Director, or designee, to fully close a portion of Arlington Court, between Arlington Avenue and Norwood Avenue, on January 16, 2025, from 7:00 a.m. through 5:00 p.m., for the purpose of a utility pole replacement, Kensington area. (District I)

FISCAL IMPACT:
No fiscal impact.

BACKGROUND:
Due to the narrow road width of Arlington Court at the work site, Pacific Gas & Electric Company (PG&E) has requested the road closure to replace the existing utility pole. PG&E shall follow guidelines set forth by the Public Works Department.

CONSEQUENCE OF NEGATIVE ACTION:
Pacific Gas and Electric Company will be unable to close the road to complete planned utility pole replacement.


c: Kellen O'Connor-Engineering Services, Bob Hendry-Engineering Services, Marke Smith-Engineering Services, Devon Patel-Engineering Services, Chris Lau-Maintenance, Brian Lande, Kensington Police Department


















Resolution 2025-06
THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
and for Special Districts, Agencies and Authorities Governed by the Board

body
IN THE MATTER OF: Approving and Authorizing the Public Works Director, or designee, to fully close a portion of Arlington Court, between Arlington Avenue and Norwood Avenue, on January 16, 2025, from 7:00 a.m. through 5:00 p.m., for the purpose of a utility pole replacement, Kensington area. (District I)


RC24-62


NOW, THEREFORE, BE IT RESOLVED that permission is granted to Pacific Gas & Electric Company to fully close Arlington Court, between Arlington Avenue and Norwood Ave...