c. Contra Costa County Supervisor Diane Burgis, Anna Cleese - District Representative
- Willow Road Repair - Pending temperate weather conditions
- Woods Harbor: Significant activity from agencies and departments since last meeting, relevant
and updates will be provided as appropriate.
- BIMAC open seat: Appointee recommendation, Roger Broom; Process on-going; Projected
appointment timeline of April 2026
- Community Clean Up Day will be October 17, 2026; Developing updated flyer with more
current messaging, please send contact information for locations for flyer placement to
Anna.Cleese@bos.cccounty.us as we need find more places to distribute the flyer; D3 staff will
be working to establish new platforms for material distribution on the island.
- Piper Road Project (January 2026 request on Future Agenda)
Piper repair update: Jan 2026 request, in progress upcoming meeting with public works
Project Funding
Funding Source: SB1 Local Gas Tax
Estimated Cost of Construction: $296,000
Project Schedule
Advertise Date: Spring 2026
Bid Due Date: Spring 2026
Working Days: 20
Estimated Construction Date: Summer 2026
Estimated Completion Date: Summer 2026
Project Updates
December 2023 - Submitted a request to FEMA for Federal Funding.
May 2024 - 35% Plans completed and are under review.
November 2024 - Project design is moving toward 65% stage
December 2024 - 65% PS&E completed and under review.
February 2025 - CEQA is approved by DCD.
March 2025 - CEQA is schedule to go to the board, after which the property acquisition progress
and 95% will begin.
Project Links
Visit our Planroom to download project bid documents obtain a planholders list, addendums,
and project questions and answers.
Notice to Bidders (PDF)
Register for the project pre-bid meeting
Bid Opening Link
Bid Results (PDF)
Contact Information
Project Manager: Abraham Lee
Email: abraham.lee@pw.cccounty.us